| Pre-Chlorinated
Pipe Rehab
Continues U.S. Growth
Most experts in the trenchless construction
industry would contend that the process of bursting
sewer pipe is still a relatively young technology. If
that's the case, then bursting of potable water lines
and replacing with pre-chlorinated pipe is in its infancy
- at least in the United States.
The state of Florida , however, in concert
with the driving force of the American Water Works Association
(AWWA) Florida section and the Florida Department of
Environmental Protection (DEP), has proven that the
method (prevalent in Europe for the last 12 years) has
the potential to be equally successful here.
Larry Ruffin, past chair of the AWWA Florida Section,
says his interest in the pre-chlorinated bursting method
started more than two-and-a-half years ago as his group
prepared for a summer seminar in August 2000. The event's
topic that year was trenchless technology. Ruffin and
his colleagues wanted pipebursting on the agenda, and
they wanted to address water as well as sewer. Bursting
potable water lines was something few knew anything
about, but it sounded viable to Ruffin.
"Logic told me," he says, "that if you
flushed or chlorinated the line before the job, you
should be able to replace the system with potable water
pipe - assuming contamination could be prevented during
the work." This could dramatically cut down the
time otherwise needed to run temporary services while
still satisfying the ever-important concern of safety.
Process intro
As Ruffin explored sources and speakers for the seminar,
he became aware of Andy Mayer , a European contractor
skilled and experienced in doing exactly what Ruffin
had in mind. Mayer agreed to speak at the AWWA event,
and organizers invited key personnel from the DEP, area
utilities and various municipalities and counties to
attend the presentation as well as a roundtable discussion.
John Sowerby, a professional engineer
with the Drinking Water Section of the Florida DEP,
was one of those in attendance. After much discussion
and investigation, following the seminar and a job-site
demonstration, Sowerby wrote a letter in November 2000
stating that the pre-chlorinated pipebursting method
would be a sanctioned practice in Florida.
"There were really two primary questions
to be answered," Sowerby says. "First, can
the pre-chlorinated method be used? Is it consistent
with the existing AWWA standards for disinfection of
pipelines and does it meet the health regulations that
should be followed? The answer to that question was
a resounding 'yes.'
"Secondly, do contractors performing this type
of work need a construction permit? Typically, we have
not required permits for repair, and we do consider
this type of work a 'repair.' "
This particular issue, Mayer says, is
a major benefit to contractors that do rehabilitation
work. It can take a great deal of time to obtain the
proper permits necessary for new construction, especially
work in environmentally sensitive areas. Because this
type of pipebursting - as long as the upsizing is no
more than two sizes - is not (under DEP regulations)
considered "new construction," those permits
and the time required to file for them are not necessary.
Moreover, according to DEP regulations, the pipe must
be installed in the exact location as the existing line.
The only way to achieve this is with pipebursting methods.
Jim Hull with CDM Engineers and Constructors
Inc., a consulting, engineering and construction firm
that became familiar with Mayer and pre-chlorinated
bursting during the seminars, also sees the permitting
issue as a plus. "Not needing the permit certainly
saves us having to go through the submittal process
and the plan review time," he says. "Those
days can add up to weeks."
With the DEP sign-off, the first pre-chlorinated
job in Florida was completed in May 2001.
Process popularity grows
As Mayer and Ruffin joined forces in 2000, continuing
their campaign to promote pre-chlorinated bursting in
Florida , Mayer formed Murphy Pipeline Contractors Inc.,
based in Jacksonville , FL. Mayer completed four pre-chlorinated
projects in Florida within two-and-a-half years. He
has three crews working, and although the crew members
are primarily European, Mayer and his teams are also
training U.S. workers so they can expand the number
of jobs and extend their geographic reach. As more Americans
learn and perfect the method, the popularity may drive
more states to sanction it.
According to Ruffin, word of the benefits
is already spreading.
"I get calls daily from other states
asking about the process," he says. "I'm happy
to send them paperwork and photos from our projects.
I'm also pleased to have people get in touch and meet
with Miami Dade County , who has really taken the acceptance
of this to the next level."
Initially, three pilot projects were done
in Florida : one with Orange County Utilities, another
in Jacksonville (United Water), and the third in Dade
County . Officials from the state of Florida were invited
to all three, one of which was done under a road, replacing
pipe 80 to 90 years old. Dade County was so pleased
that they subsequently purchased equipment so they could
do the work themselves.
"We showed the people from the state
of Florida that a 98 percent savings in time could be
realized, along with a 75 percent savings in cost compared
to open-cut methods)," Ruffin says. That was no
fluke. Ruffin describes the method as "getting
better with each job," producing time and cost
savings very consistently, if not a little better.
Mayer's estimation, a bit more conservative
but still quite impressive, is that pre-chlorinated
bursting is 50 to 60 percent faster (than open-cut methods).
"Obviously, the faster you go," he says, "the
better your labor costs are."
Everglades test
Most recently, pre-chlorinated bursting was employed
at Everglades National Park . Spanning the southern
tip of Florida Bay , the area is the only subtropical
preserve in North America . Mayer and his Murphy Pipeline
crew were subcontracted by CDM to replace 25,000 feet
of 2, 4 and 6-inch water line near Flamingo, FL. Mayer
believes this may be the largest pre-chlorinated bursting
project undertaken in the United States, even though
it's fairly common in terms of what he's used to doing
in Europe.
"If we were trenching on this project,
we'd essentially abandon the old pipe after trenching
in a new line beside it," CDM's Hull says. "This
process saved us a tremendous amount of time."
The Murphy Pipeline crew averaged installing
3,000 feet of line a week in Flamingo with their Hammerhead
HydroBurst HB3038, a compact unit with 30 tons of pulling
force that is ideal for bursting cast iron, clay, concrete
or other fracture prone pipe up to six inches in diameter.
But, Mayer says, one day they burst 2,900
feet. Even more impressive than the speed is the lack
of disturbance. As one could guess, the National Park
Service is quite particular about work being done in
what Mayer describes as "living areas" - places
where foliage and wildlife are abundant. In fact, the
park is known for its rich bird habitat. And, it's the
only place in the world where alligators and crocodiles
exist side-by-side. According to the National Park Service,
Everglades National Park has been designated a World
Heritage Site, an International Biosphere Reserve and
a wetland of international importance. In fact, the
National Park Service diligently witnessed several demonstrations
to ensure authenticity before they bought into the bursting
process.
"Maintaining the environment was
a primary challenge," Mayer says. "But, one
reason the National Park Service is so pleased with
this type of method is the minimal disruption. Essentially,
we can come into an area on day one to set-up. Then,
we have a day to burst. On day three, we're restoring
the few pits required. It's often very difficult to
tell that we were even there."
Hull concurs. "This method pleases
us most because it pleases the client," he says.
"The disruption to the visitor'experience and damage
to cultural resources with open cutting would have made
the project considerably more intrusive. We didn't have
that with pre-chlorinated bursting."
Mayer estimates that what took his crew
just seven weeks to complete may have taken a contractor
digging and trenching a few months, not including the
permitting process. Temporary services would have had
to be devised while pipe was removed and replaced. He
believes the success of this job may lead to other National
Park Service projects.
"There is talk of another three jobs
right off the bat," Mayer says. "That's attributed
to the work of a very experienced, diligent, hardworking
crew using dependable equipment."
Future of pre-chlorinated bursting
Mayer credits Larry Ruffin for his vision and push to
bring this method to the United States . Ruffin praises
Mayer for his ability to sell the necessary personnel
on the fact that pre-chlorinated bursting is practical
and safe. They both commend officials like John Sowerby
(Florida DEP) for their interest in continuing to find
better methods that can cut time and restoration costs.
And, they both believe that - although it may take some
time - pre-chlorinated bursting is a process that will
flourish in the United States.
"We are all creatures of habit,"
Ruffin says. "The simple fact that this is a different
method that not everyone is familiar with is the primary
reason that it's not done more often and in other states."As
officials learn more about it and support it, there
will be more pre-chlorinated jobs. And, there will be
more states that sanction the process."
Mayer believes the type of pipe may have
something to do with the relatively slow acceptance.
"Pre-chlorinated bursting is done with HDPE, and
we use electric fusion and couplings," he says.
"There's no sense in using pipe good for 70 years
and fittings good for 20 (as may be the case in other
applications)."
Most areas in the United States , he says,
have preferred to use PVC or ductile iron. "HDPE
is primarily used in Europe , so we just need to sell
the material before we can sell the method. But, engineers
are catching on."
Mayer says he "stumbled onto"
something that we did not have in the United States
, and he immediately saw a lot of potential. Ruffin
feels good to have been a part of this new dawn of the
U.S. trenchless industry. "Contractors go from
doing a job that may have taken a year or more when
you consider the time required to obtain permits and
doing the construction with open-cutting, to getting
it done in two weeks," he says. "That's an
exciting change. The group that has really brought this
to the forefront is the AWWA Florida section. They helped
convince officials that came in with an open mind that
this is a safe and better method."
Rehabilitation Technology
, March 2003
|