|
London Native Shares
Pre-Chlorinated Pipe-Bursting Secrets
The method is a common practice in the United Kingdom
and is catching on elsewhere
When Andy Mayer moved to the United States
from London, he was shocked to discover that pipe bursting
water mains using the pre-chlorination method was not
a commonplace practice. Contractors in England adopted
the practice more than a decade ago when the country
ran out of underground space to install new pipeline,
and have used it to replace nearly every water main
since.
“It's a shame that more water companies
and contractors are not familiar with the pre-chlorinated
pipe-bursting method,” he says. “It's a
real timesaver for the contractor, and it saves the
water company money, too.”
In a global economy, many construction
and engineering methods develop on a local basis and
later become a regional or national industry standard.
That's what Mayer, president of Jacksonville, Fla.-based
Murphy Pipeline Contractors, Inc. (MPC), hopes will
happen with the pre-chlorinated pipe-bursting method.
While his 22-month-old daughter “Hanna Banana”
remains the “love of his life,” Mayer has
made it his personal mission to bring pipe bursting
water mains with the pre-chlorinated method to other
parts of the modern world.
| “I
believe, in the next five years, that pipe bursting
will be the preferred method for water main replacement
in America” |
U.K. water companies underwent a major
privatization in the mid-1990s, when there were only
14 major water companies serving nearly 58 million people,
Mayer says. At the time, many of the cast-iron water
mains were leaking up to 30 percent of the water pumped
into them, creating hefty repair costs and also huge
revenue losses for water companies. As a result, the
water companies made a large-scale investment to install
new mains to recover water loss and also reduce costly
leaks. Today, nearly 90 percent of all water mains in
the U.K. are replaced using the pre-chlorinated pipe-bursting
method. Mayer says a single contractor in his native
country typically bursts up to 80 miles of water main
annually.
Mayer moved to Florida in May 2000, recognizing
that the U.S. market was literally untapped. By November
of that year, the Florida Department of the Environmental
Protection Agency had approved the method of pre-chlorination
and pipe bursting for water mains. Since then, MPC has
installed more than 50,000 feet of water main using
the pre-chlorinated pipe-bursting method. In addition,
Mayer has served as a consultant on major projects throughout
the United States . By working with the American Water
Works Association (AWWA) in Florida to spread the word
about the benefits of employing the pre-chlorinated
pipe-bursting method, Mayer has been able to help Florida
water companies accept the method as an acceptable means
of water main rehabilitation.
“I believe, in the next five years,
that pipe bursting will be the preferred method for
water main replacement in America,” he says.
The Method
Pipe bursting is both cost-effective and environmentally
friendly. The chief advantage of this method is that
contractors can replace pipeline without having to dig
up the old main. It is ideal for all urban applications
where an existing pipeline has exceeded its useful life,
and can be used beneath buildings, roads, rivers, or
bridges — thereby avoiding traffic delays and
minimizing inconvenience to residents and businesses.
Pipe bursting is one of the most cost-effective methods
of replacing pipes or upsizing them to meet increased
demand. By using this system, the pipe is shattered
into small pieces and pushed laterally into the surrounding
earth. The original pipe diameter is replaced or upsized
using an expander, and the replacement pipe is then
towed into the new borehole.
Using this method on water mains costs
less than traditional open-cut or relocation methods.
One reason for this is that pre-chlorinated pipe-bursting
systems use existing utility location and easements,
lowering design and engineering fees associated with
a utility relocation design. Pre-chlorinating and pre-pressure
testing the HDPE water main above ground, prior to installation,
provide significant cost savings and are key to the
overall process, as they eliminate the expense and disruption
of providing homeowners with a temporary water supply.
The Project
MPC recently completed a pre-chlorinated pipe-bursting
project in Fort Pierce, Florida, during which Mayer's
team replaced about 13,000 feet of water main in eight
weeks. A crew of six handled the project on Indian River
Drive, which is classified as a scenic state highway.
Fort Pierce Utilities Authorities began
looking into replacing the 6-inch cast-iron pipes with
6-inch HDPE pipes when they learned the water main was
more than 65 years old, says engineer David Mellert.
“There was a history of complaints associated
with the water main related to water pressure and clarity,”
he says. “We realized this project was going to
require some special attention beyond the industry standards
because the area had limited working space, high-end
homes with expensive driveways, and heavy traffic. In
addition, because of easement issues, open cutting in
the middle of the road was not an option. So, we evaluated
different options to see which method was most compatible
with our needs.”
When Mellert talked to Mayer about employing
the pre-chlorinated pipe-bursting method, he saw it
as a viable, cost-cutting alternative. In addition,
the system Mayer described would cause less disruption
to the prominent neighborhood residents, Mellert says.
“After evaluating various alternatives, we selected
the pre-chlorinated system because the price, technology
and method most closely meshed with our requirements,”
he says. “Murphy Pipeline Contractor's technology
was a good fit.”
Using the pipe-bursting method saved Fort
Pierce about 30 percent over an open-cut method in excavating
and road restoration, as well as in permit approval
and project time, he estimates, “and customer
satisfaction is priceless.”
MPC purchased a HAMMERHEAD HydroBurst
® HB3038 Static Pipe-Bursting System for the Fort
Pierce project because Mayer and his team had rented
and used it successfully on a previous job “and
found it to be a reliable and efficient rig,”
he says. The HB3038 is a compact unit with 30 tons of
pulling force ideal for bursting cast-iron, clay, or
other fracture-prone pipe up to 6 inches in diameter.
| “Residents
really like that we're generally only outside their
house for one day instead of three or four weeks,
as you'd see with a traditional open-cut method.” |
Mayer's crew burst an average of 400 feet
of pipe in about two hours each day. The rest of the
day the crew handled restoration work, pre-chlorinating
and pre-pressure testing pipes. “The main was
cut and capped, on average, by 8:30 a.m. each day. Only
the section scheduled to be burst was without water
during that time,” Mayer says. “The rods
were inserted into the de-commissioned main from the
launch pit and pushed to the receive pit. The rods were
then connected to the bursting blade, bursting expander
and the pre-chlorinated pipe. The pullback started.
By 10:30 a.m., the pipe was back in the launch pit and
the bursting equipment was removed before lunch.”
The new HDPE service lines to homes were
installed with the aid of a 2-inch HAMMERHEAD Mole.
The mains were connected with a top tee or sidesaddle
using an electro-fusion fitting. Next, the new service
was connected to the main and flushed. After flushing
the connection to the meter, a faucet was opened to
expel any excess air, and then the water main was pressure
tested a second time before putting it back in service.
Mayer says his two weeks of planning the pre-chlorination
process and excavation work around the residents' schedules,
fire hydrants, and valve positioning always pays off.
“Residents really like that we're generally only
outside their house for one day instead of three or
four weeks, as you'd see with a traditional open-cut
method,” he says.
Fort Pierce Utilities Authorities also
took measures to mitigate the disruptions to residents,
Mellert says. “One of the things we did was notify
residents about the project and the minor disruptions
it would cause. We also set up a hotline for residents
to call in with their questions or concerns,”
he says. “Then, when we knew residents would be
directly affected by the project, we sent an employee
to their home to notify them that it would affect them
personally. We wanted the residents to feel they were
part of the solution, not part of the problem —
and we even encouraged them to come watch the work in
progress.”
Pleasing area residents was his first
priority, Mayer says. And it showed. After the first
two weeks on the project, homeowners were bringing the
MPC crew cookies and drinks. One even invited them for
a St. Patrick's Day party. “We had the best food:
corn beef and cabbage — and Guinness beer,”
he said. “It was almost like back home.”
Mellert says it's true residents were
happy with Mayer and his team. “They thought he
was the greatest thing since sliced bread,” he
says.
April Goodwin, Technical
Writer
Des Moines, Iowa
|