| Pre-Chlorination
Procedure for Rehabilitation of Existing Water Lines
Method One
All work involving the renewal of water
lines using pipe insertion techniques shall be carried
out as hygienically as practicable in accordance with
applicable specifications, procedures, codes, regulations
and laws of governing regulatory authorities, as applicable
and the American Water Works Association with all reasonable
steps being taken to avoid contamination of water supplies.
Inform the water provider immediately
of any renal dialysis patients or other critical supplies
which may be affected.
Where possible the inside section of the
replacement pipe shall be inspected for debris before
any work commences and any visible matter removed.
The new length of main should be positioned
and jointed on the surface, each end capped and charged
with chlorinated water. A free chlorine residual of
25 mg/L should be maintained for a minimum contact time
of 24 hours.
Where coils are used, they should be laid
on their side rather than in a vertical, making sure
that air can escape, and charged slowly to ensure tablets
(which must be the instant dissolve type) are evenly
distributed. The ends of the pipe should be closed and
sealed at all times and the disinfection/swabbing procedure
repeated if a coil is cut and not used until the next
day. Normally, the maximum period between emptying chlorinated
water from a coil and subsequent laying/commissioning
shall not exceed two hours.
Access holes should be kept dry as possible,
the excavation being taken 12” below the pipe
invert to prevent ingress of contamination.
The existing main shall be cut and capped
at the access holes and the services disconnected. All
fittings including the internal surfaces of the existing
main, should be sprayed or rinsed with dilute solution
of freshly prepared chloros of 1-5%. This should be
freshly prepared on sites as dilute chloros solutions
will deteriorate after a week.
Approximately one hour before being laid,
the length of main to be installed shall be drained
of super-chlorinated water and capped.
Note: The environment to which the chlorinated
water is to be discharged shall e inspected. If there
is any possibility that the chlorinated discharge will
cause damage to the environment, then a neutralizing
chemical shall be applied to the water to be wasted
to neutralize thoroughly the residual chlorine. Where
necessary, federal, state, provincial and local regulatory
agencies should be contacted to determine special provisions
for the disposal of heavily chlorinated water.
During the reconnection operation all
pipework and fittings shall be rinsed or sprayed with
chloros solution (1-5% strength).
Once the main has been laid it shall be
chlorinated to 50 – 100 mg/L and stood for three
hours or 300 mg/L and stood for 15 minutes before being
flushed, swabbed and commissioned.
Notes: The discharge of large quantities
of water from a main must be planned to avoid flooding
or causing dangerous road conditions.
After thorough flushing, two consecutive
acceptable bacteriological samples, taken at least 24
hours apart, shall be taken downstream by fully qualified
rehabilitation staff who are involved in the valving
operations. Where no pollution hazard has been present,
the main can be returned to service prior to completion
of bacteriological testing in order to minimize the
time customers are without water. Where there is any
doubt, the affected section of main shall not be re-commissioned
until satisfactory bacteriological sample results have
been obtained. If positive bacteriological samples are
recorded, the water system and the appropriate Department
of Environmental Protection District Office or appropriate
approved County Health Department shall be notified
immediately.
Only fully trained and certified personnel
shall be allowed to undertake disinfection and piece-up
operations involving mainlaying, fittings, installation
and all reconnections.
All samples, when taken, must have a maximum
holding time of 30 hours.
Wherever practical, work should progress
in such a way that location of the commissioned water
slug is known and not distributed widespread throughout
the system until the bacteriological sample is confirmed
and satisfactory.
Revised Edition 19 December
2000
Pre-Chlorination
Procedure for Rehabilitation of Existing Water Lines
Method Two
This procedure outlines the steps to be
followed when pre-chlorination of the new water line
in used to enable the process of pipebursting to replace
an existing water supply line. It is essential that
all precautions are taken in order that a water quality
is maintained and standards are not compromised.
Definitions
Pipebursting – The replacement of
an existing water line by bursting out the main using
a moling devise and simultaneously introducing the new
pipe.
Sliplining – The replacement of
an existing water line by inserting a smaller diameter
pipe inside the old main. The water quality considerations
of this procedure are also appropriate to sliplining
where the sliplining process of laying and commissioning
is undertaken during one operation in the same pattern
as pipebursting.
Starting the Scheme
Ensure all persons are fully qualified,
medically cleared to work on restricted operations and
are fully competent in company procedures of hygiene.
Check with the water supplier’s
system operations team for potential problems that may
occur to the flow patterns during the works.
Sample incoming water upstream of the
pipebursting project, at the customer’s tap to
determine that existing water quality is satisfactory.
As a guide it is recommended to take samples at least
10 working days before the project is started. This
will allow three days for the bacteriological sample
to pass and seven-day card warning notice to be sent
to the affected customers. A 24-hour warning card will
also be delivered to notify the customers of the actual
times water supplies will be interrupted.
Disinfection
An appropriate solution for disinfection
of tools, equipment, fittings and materials to be used
in pipebursting is made up of minimum 1-5% of available
chlorine. Fresh solutions should be made regularly as
dilute chloros solutions deteriorate after seven days.
Old solutions should be disposed of after dechlorination.
No chlorinated water shall be discharged to a water
course or surface drain.
Disinfection should be carried out using
hand held spray equipment and care taken to ensure the
whole surface is treated.
All tools and equipment to be used in
contact with water shall be disinfected using the appropriate
strength chlorine solution detailed above, with hand
held spray equipment. Special care needs to be taken
with hired-in equipment to ensure that no contamination
risk is present and off-site washing may be necessary
before disinfection prior to use.
All fittings and materials used in pipebursting
shall be stored hygienically and reasonable measures
taken to exclude vermin, debris, or dirty water. Ensure
all fittings and materials are disinfected before installation
with hand held spray equipment using the appropriate
strength chlorine solution detailed above.
Preparation of the Coil
An area to prepare the new pipe for pre-chlorination
shall preferably be of hard standing (asphalt, concrete
or stone), which is free from any visible contamination.
When using coiled pipe, this should be
laid on its side rather than in a vertical position,
making sure that air can escape.
One end of the coil shall be capped then
at the other end, firstly insert a clean swab, then
install the correct amount of tablets for the size of
pipe to be pre-chlorinated, (tablets should be the instant
dissolve type), then the cap fitted to this end (ensure
the caps and pipe ends are disinfected using the appropriate
strength chlorine).
Slowly charge the new pipe allowing the
tablets to be distributed evenly.
A free chlorine residual of 25 mg/L should
be maintained for a minimum contact time of 24 hours.
After thorough flushing the new pipe shall
be sampled at each end at intervals of 1200 feet, only
by fully qualified rehabilitation staff, who will then
fill in a log book/passport form detailing the date,
coil number and time sample was taken. A copy of this
form will also be taped to the coil to ensure the correct
pipe is referred to.
Note: The environment to which the chlorinated
water is to be discharged shall be inspected. If there
is any possibility that the chlorinated discharge will
cause damage to the environment, then a neutralizing
chemical shall be applid to the water to be wasted,
to neutralize thoroughly the residual chlorine. Where
necessary, federal, state, provincial and local regulatory
agencies should be contacted to determine special provisions
for the disposal of heavily chlorinated water.
Once two consecutive sets of acceptable
bacteriological samples, taken at least 24 hours apart,
have been obtained, the coil must be stored hygienically
with the ends sealed and secured to prevent tampering.
The date and time of the cleared samples must be entered
onto the relevant log book/passport sheet for that coil.
The coil must be used in 14 days of clearance or it
will need to be flushed and re-sampled.
Pre Chlorinated Coil
When required for use, cleared coils will
be drained and sealed at both ends using two pressure
test ends. Care must be taken to avoid contamination,
and all fittings must be disinfected by spraying using
the chloros solution. The coil will be transported to
site and used the same day.
Only coils with valid log book/passport
attached and which remain hygienically secure will be
used for pipebursting. Others will be returned for re-sampling.
Access holes should be kept as dry as
possible, the excavation being taken 12” below
the pipe invert to prevent ingress of contamination.
The existing main shall be cut and capped at the access
holes and the services disconnected. All fittings including
the internal surfaces of the existing main, shall be
sprayed using the dilute solution of freshly prepared
chloros of 1-5% of available chlorine.
A clean chloros soaked sway shall be inserted
behind the pulling eye attached to the coil.
Pipeburst the dead section of main.
Cut away the pulling eye and swab and
install a blank flange with a sample tap.
Re-chlorinate the new section of main
using instant dissolve tablets, ensuring that enough
tablets have been inserted to reach a minimum free chlorine
residual of 50 mg/L.
After two hours of super-chlorination,
check there has been no chlorine loss, after thorough
flushing (checking chlorine levels frequently) until
water samples are equal to the sample of the incoming
water.
Note: If there is a possibility that the
chlorinated discharge will cause damage to the environment,
then a neutralizing chemical shall be applied to the
water to be wasted to neutralize thoroughly the residual
chlorine. The discharge of large quantities of water
from a main must be planning to avoid flooding or causing
dangerous road conditions.
Samples should be taken downstream by
fully qualified rehabilitation staff who are involved
in the valving operations. Where no pollution hazard
has been present the main can be returned to service.
Only fully trained and certified personnel
shall be allowed to undertake disinfection and piece-up
operations involving mainlaying, fittings installation
and all reconnections.
All samples, when taken, must have a maximum
holding time of 30 hours.
Revised Edition 19 December
2000
Please contact
us for more information.
|