top of page

Sliplining

Sliplining is completed by installing a smaller, carrier pipe into a larger host pipe, grouting the annular space between the two pipes, and sealing the ends. The trenchless method is generally a cost-effective rehabilitation method to replace water and sewer force mains.

 

Sliplining is one of the oldest forms of trenchless technology. The most common material used to slipline an existing pipe is high-density polyethylene (HDPE). Continuous sliplining uses HDPE pipe that is fused into long lengths prior to installation. The HDPE pipe is pulled through the existing host pipe starting at an insertion pit and continuing to a receiving pit.  Long installation distances of up to 5,000 feet are possible.​

Potential limitations are the new pipe will generally have a reduced cross sectional area due to installing a smaller sized pipe, thus reducing flow rates and capacity. Hydraulic calculations need to be considered.For pipeline projects that need to maximize final Internal Diameter, CompressionFit HDPE pipe lining can add value over sliplining.

SPECIFICATIONS

Increased Flow Rates Over Slip Lining

  • Tight fitting HDPE provides maximum Internal Diameter delivering greatest flow

  •  Smooth wall of HDPE (150 c-factor) reduces friction and pumping costs

  • o grouting is required due to compressive tight fit of new HDPE

Minimal Schedule
and Impact

  • Production rates of up to 5,000 feet in a single pull  

  • 91% less excavation than open cut

Solution to the Problem

  • Fully structural HDPE can be installed if the host pipe has no integrity

  • Semi-structural HDPE can be installed if the host pipe has some integrity, yet increase strength, span holes and provide corrosion protection

  • Thin walled HDPE can be installed if the host pipe is sound, but joints are leaking or corrosion protection is required

Existing Utility Path Followed

  • No available easement?  We won't need one

  • Design hours reduced as utility relocates are irrelevant

bottom of page