Compression Fit HDPE Pipe Lining Case Studies

CompressionFit HDPE pipe lining

MUNICIPAL - MINING - GAS - FEDERAL - INDUSTRIAL - PRIVATE - MILITARY - UNIVERSITY

 

Case Study: 2014 Trenchless Project of the Year

Client: Gulf Coast Water Authority, Texas

Technology: Compression Fit HDPE pipe lining

Details: 6,800 feet of 39" PCCP water transmission main replaced with HDPE PE4710 DR 17

Trenchless Technology Project of the Year
Compression Fit HDPE pipe lining
Swagelining Sliplining
Close Fit Sliplining

Case Study: Water Transmission Main Replacement
Technology: Compression Fit HDPE pipe lining
Details: 9,950 feet of 42" Cast Iron water transmission main replaced with HDPE PE4710 DR 17

Compression Fit HDPE
Water transmission main replacement
Trenchless technology equipment

Case Study: Sewer Force Main Replacement
Technology: Compression Fit HDPE pipe lining
Details: 54" PCCP sewer force main replaced with HDPE PE4710

Large diameter HDPE butt fusion
Compression Fit pull head
HDPE pipe lining process
Large diameter sewer force main replacement

Case Study: Sewer Force Main

Case Study: Sewer Force Main Replacement
Client: Jacksonville, Florida
Technology: Compression Fit HDPE pipe lining
Details: 2,300 feet of 24" Ductile Iron sewer force main replaced with HDPE PE4710 DR 17

Florida Swagelining Case Study
Florida HDPE pipe fusion
Florida HDPE pipeline
Florida close fit sliplining

Case Study: Water Transmission Main

Case Study: Water Transmission Main Replacement
Client: Houston, Texas
Technology: Compression Fit HDPE pipe lining
Details: 7,600 feet of 30" PCCP water transmission main replaced with HDPE PE4710 DR 32.5

Swagelining Texas
Texas close fit sliplining
HDPE tight fit lining Texas
HDPE connections large diameter water

Case Study: Water Transmission Main Replacement
Client: Colorado Spring, Colorado
Technology: Compression Fit HDPE pipe lining
Details: 1,300 feet of 20" Steel water transmission main replaced with HDPE PE4710 DR 13.5

HDPE butt fusion
Butt fussion welding
20-inch steel water main replacement
Compression Fit Swagelining pipe lining

Case Study: Water Transmission Main

Case Study: Water Transmission Main Replacement
Client: Amarillo, Texas
Technology: Compression Fit HDPE pipe lining
Details: 5,300 feet of 30" Cast Iron water main renewed with HDPE PE4710 DR 32.5

Texas Swagelining
Swagelining Water Transmission Main
Close Fit Sliplining
HDPE Pipe Lining Compressive Fit

Case Study: Chilled Water Lines

Case Study: Chilled Water Lines
Client: Texas A&M University
Technology: Compression Fit HDPE pipe lining
Details: 6,400 feet of 18" & 20" Steel Chilled Water Lines replaced with HDPE PE4710 DR 26

HDPE Pipe Lining Texas Case Study
HDPE pipe Texas A&M University
HDPE pipe chilled water lines
Trenchless HDPE pipe lining

Case Study: Sewer Force Main

Case Study: Sewer Force Main Replacement
Client: City of Sioux Falls, South Dakota
Technology: Compression Fit HDPE pipe lining
Details: 8,709 feet of 36" Ductile Iron sewer force main replaced with HDPE PE4710 DR 21

Wastewater Infrastructure replacement
ductile iron pipe ovality
36-inch CompressionFit Video
CompressionFit pipe lining

Case Study: Sewer Force Main Replacement
Client: Douglasville-Douglas County Water and Sewer Authority, Georgia
Technology: Compression Fit HDPE pipe lining
Details: 36" Ductile Iron sewer force main replaced with HDPE PE4710 DR 21

Lifting HDPE pipe
36" Sewer force main replacement
modified close fit slip lining

Case Study: Water Transmission Main Replacement
Client: Southeastern Oakland County Water Authority (SOCWA), Michigan
Technology: Compression Fit HDPE pipe lining
Details: 16" Cast Iron water main replaced with HDPE PE4710 DR 13.5

16" waterline replacement
Murphy Pipelines
Compression Fit HDPE pipe relining

Case Study: Sewer Force Main Replacement
Client: Madison Sewerage District, Wisconsin
Technology: Compression Fit HDPE pipe lining
Details: 36" PCCP sewer force main replaced with HDPE PE4710 DR 32.5

Butt fusion HDPE pipe
36-inch CompressionFit
Line stop HDPE bypass

Case Study: Raw Water Main

Case Study: Raw Water Main

Client: Dillon, Colorado

Technology: Compression Fit HDPE pipe lining

Details: 1,007 feet of 24" RCP Raw Water Inverted Siphon with HDPE PE4710 DR 32.5

Colorado HDPE pipe lining Case Study
Large Diameter HDPE pipe fusion
Compression Fit HDPE pipe lining
CompressionFit HDPE pipe lining pit

Additional Case Studies

ASCE Pipelines Swagelining

ASCE Pipelines: Renewing Life of Large Diameter Pressure Pipelines with HDPE Pipe Lining Technology

Trenchless water line rehab

Full Structural Case Study: 24" Water Main with HDPE DR 11

Trenchless large diameter water transmission main replacement

Trenchless Technology Magazine: Swagelining Technology Renews Life of Pipelines

HDPE pipe lining Los Angeles California

Los Angeles, California 36" & 24" Water Transmission Main CompressionFit

CompessionFit HDPE pipe lining

Boulder, Colorado 16" High Pressure Water Main Case Study

HDPE Lining Subsea

Oil & Gas Case Study:

Subsea Pipeline

Mining HDPE pipe lining

Mining Case Study:

Tailings, Slurry, Backfill Pipelines

Fully structural water lining

NASTT No-Dig Paper: Fully Structural Renewal of 39" PCCP Water Main with CompressionFit and HDPE

HDPE lining High Pressure Pipelines

Oil & Gas Case Study:

High Pressure Water Injection Pipeline

Water injection HDPE pipe lining

Oil & Gas Case Study:

Water Injection Riser

Swagelining HDPE Lining

Journal Achievements in Materials & Manufacturing: CompressionFit

Asia trenchless water line replacement

Asian Water: Rehabilitating Hong Kong's Water Mains

Close fit slip lining Colorado

Greeley, Colorado 27" Water Transmission Main CompressionFit

Swagelining Thin Walled HDPE

Thin Walled Case Study: 40" Water Main with HDPE DR 51

Feasibility Study HDPE pipe lining

Case Study: Feasibility Analysis

TESTIMONIALS

 

"The City of Fort Lauderdale was dealing with aging infrastructure that due to erosion from the brackish saltwater was virtually disintegrating. We knew that we needed to provide the quickest solution possible for our community, and the technology utilized allowed for the replacement of the compromised FM in record time. This trenchless process, coupled with the use of HDPE and its 100 plus year life span, is quite simply the best available technology out there."

Omar Castellon, P.E. Assistant Public Works Director – Engineering, City of Fort Lauderdale